Has the project drawings been checked, is the scope of works confirmed between installer and builder/developer.

Has the installer attended the Dincel academy (proof of attendance can be identified by producing an attendance certificate).

Site-Specific ITP has been developed for wall installation.

Site-specific SWMS has been developed for wall installation.

Waterproofing detailing has been finalized by project consultants and/or waterproofing contractor (i.e membranes, sealants, waterstops and ag lines as required).

Fall protection in place and complies with the relevant Sfe Work requirements.

Dincel panels have been unloaded adequately and no panels or components have been damaged.

Wall location has been marked out via survey or similar to ensure accurate wall placement.

Has the wall substrate been trowelled to the required workable finish and handed over to the installer clear of rubbish and free of debris.